Sturgeon County has contracted the following 17 bridge files for required maintenance to Alberta Highway Services. This work is scheduled to be completed by March 31, 2012. The following information is a schedule of work to take place (subject to change).
BF indicates the Bridge File # for each project.
Bridge File 215 (located on Twp Rd 554) – Division 3
Monday, January 30
Duration: 5 days
Completion Date: February 4, 2012
UPDATE: Bridge File 1636 (Located on RR10) – Division 3
Saturday, February 4, 2012
**The road will be closed for approximately 20 days.
UPDATE: Bridge File 70827 (located on RR273) – Division 3
Saturday, February 4, 2012
The road will be closed for approximately 10 days.
*BF indicates the Bridge File # for each project.
* Tributary - is a creek or stream flowing in to a river or lake
* Watercourse - is a natural or man made drainage ditch which may or may not lead to a river or tributary
2012 Proposed Road Construction Projects
Local Road Construction Program
Range Road 274 - Hwy 633 to Twp Road 544
Range Road 241 - Cameron Park Subdivision to Twp Road 552
Twp Road 552 - Range Road 241 to Range Road 240(Sunnyside Road)
Range Road 234A - Hwy 37 to Twp Road 551(Contracted)
Grid Surfacing Program
Local Road Paving (Contracted)
Twp Road 554 - Range Road 251 to Range Road 245
Range Road 230 - Hwy 37 north 1.6km
Range Road 230 - Intersection - Hwy 37 & Range Road 230
Twp Road 544 - Hwy 779 to Range Road 11
Old Fort Trail Overlay - Hwy 15 southeast
Subdivision Paving
Riviere Qui Barre - End of existing pavement @ Camilla School north to Hwy 44
Local Road Shoulder Pulling Program
Fifth Meridian (Range Road 10) - Hwy 37 to Twp Road 554
Range Road 260 - Twp Road 564 to Twp Road 572
Range Road 231 - Twp Road 560 to Hwy 643
Twp Road 570 - Range Road 10 to Range Road 11
Contracted 2011 Road Construction
SUNNYSIDE ROAD SUB GRADE STABILIZATION AND PAVING
CONTRACTOR: CARMACKS CONSTRUCTION: Carryover of cleanup and inspection to be completed in 2012.
Unfortunately, unavoidable inconveniences such as road closures, detours, slower moving traffic,
rougher road conditions and higher noise levels may occur as result of this constructions.
The Transportation department reminds you to slow down and use caution when driving through road work areas. Thank you for keeping the road crews safe.